Ah-am Logistics Complex 2 (Under Construction)

Project Overview

  • Location : The entire area of 297 Songdo-dong Yeonsu-gu Incheon
  • Project Size : 2,571,000㎡
  • Project Period : 2014 ~ 2022
    • Stage 1-1 : 2015~2017 (922,000㎡)
    • Stage 1-2 : 2018~2019 (661,000㎡) - Stage 2 : 2020~2022(1,043,000㎡)
Project Overview
Each FacilityArea (㎡)Composition Rate (%)Remarks
Total 2,571,180 100.0%-
Subtotal 2,242,040 87.2%
Type 1 Port Hinterland Complex1. Complex Logistics and Manufacturing Facilities 1,156,035 45.0%
2. Business and Convenience Facilities - 0.0%
3. Public Facilities 1,086,005 42.2%
‧ Road 518,823 20.2%
‧ Afforestation 542,438 21.1%
‧ Other Public Facilities 24,744 1.0%
Type 2 Port Hinterland Complex 329,140 12.8%

Traffic Plan